Choosing a Processing Destination

When one downstream destination exists and there are two or more upstream entities competing to get there, you can use priorities. In the following example, two entities at different locations are both trying to get to Process C.

 

If you want the entity coming from Process B to have priority and go to Process C first, define a priority in the destination field for the routing of Process B. In the following example, we entered a priority of 10 for the routing of the entity Casting at the location Process_B.

 

How to enter a priority for a destination:

Enter a priority value directly in the destination field, making sure there is a comma separating the destination and priority.

or...

Click the Destination... button and enter the priority in the appropriate field.